Progress on Harbour

Posted by | Community Facilities, Greystones, Harbour | No Comments

The North Harbour Wall is 35% complete and the South Wall is 80% complete. Around 3500 of the 5000 large blocks have been cast. During the Winter the project became 3 months late. However February was a calm month and some time was made up. First the seabed is flattened and a fibre layer is laid, then about 10 (depending on the depth) large blocks are laid on top of each other, locking bars are inserted and rock armour is placed outside from the barge or shore. This is a…

Read More