Greystones Harbour Facilities Delayed

Posted by | Harbour | No Comments

At a recent Community Liaison meeting it was announced that the marine works for Greystones Harbour, including 2 Public slipways, would be completed by October 2010. These have been delayed by the swell generated by the easterly wind over the Winter. Limited access will be provided to local clubs to the completed slip over the Summer.

Read More

Greystones Harbour Latest Update

Posted by | Greystones, Harbour, Local Work, Priorities, Uncategorized | No Comments

The December photo shows how far work has progressed with about 15 machines working on it. The marine works, including 2 public slipways, should be complete in June this year. The harbour will not open to the public this year as considerable work must be done on the land side. The walls are solid blocks protected by rocks and then antifers placed on top. These concrete castings appear white in the photo and their function is to break up the waves before they hit the wall. During the heavy storms…

Read More

Mitchell confident harbour will be completed

Posted by | Harbour | No Comments

Some candidates in the elections have been spreading alarm about the Visionary Project. I am confident it will be completed because: 6 Years ago I arranged that the Council would employ a top lawyer on this complex project and the selection criteria included considering the financial strength of the bidders. The Council is in a strong position because of this preparation. We expect to open the harbour, marine clubs, public slipways and public square in the Autumn 2010 and the Southern half of the hoardings will come down then. Work…

Read More

Confident Greystones Harbour will be completed

Posted by | Achievements, Greystones, Harbour | 1,247 Comments

Simon Harris and Councillor Tom Fortune have been on the radio suggesting it wont be completed for 15 years, wanting firm information and whinging. Both of them campaigned to reject this visionary harbour project and they should check the facts before making these statements spreading alarm.   The harbour works are running about 4 months late because the waves have made it more difficult to lay the blocks than was anticipated. This work is now going to be done on two shifts over the Summer to try to complete most…

Read More

Progress on Harbour

Posted by | Community Facilities, Greystones, Harbour | No Comments

The North Harbour Wall is 35% complete and the South Wall is 80% complete. Around 3500 of the 5000 large blocks have been cast. During the Winter the project became 3 months late. However February was a calm month and some time was made up. First the seabed is flattened and a fibre layer is laid, then about 10 (depending on the depth) large blocks are laid on top of each other, locking bars are inserted and rock armour is placed outside from the barge or shore. This is a…