• Codling will be the largest windfarm in Ireland with twice the power of Moneypoint, the largest thermal station. It will be very visible from the coast from Greystones to Newcastle & Wicklow Town. It is essential that the area is made feel connected and involved with the project via jobs, information, tourism, boat movements & […]

  • Options. North Pier. Access problems for commercial vehicles and 600 residents, and safety on pier. 12 residents have written complaining of danger and intimidation and want to be represented. South pier. Enough space? Reconfigure boatyard? Need for subsidy to replace income, truck access through children launching? Alter pier? Might work. Placing a pier/pontoon out from […]

  • On Monday the Councillors met the 3 fishermen. And on Thursday met them and the marina operators, Sisk, Council staff and Bord Iasce Mara. Options. North Pier. Access problems for commercial vehicles and 600 residents, and safety on pier. 7 residents have written complaining of danger and intimidation and want to be represented. South pier. […]

  • Considerable commercial vehicle traffic including oil tankers on a 24 hour basis in a dense residential area with narrow footpaths designed as a residential cul de sac. Fishing HGVs are driving dangerously (including turning) where many, including children, are hauling dingies & canoes across a path & launching. 2 children were almost run down in […]

  • The developer of the harbour houses has proposed changes which mean they now propose to overlook Mt. Haven behind the railway line. I have objected as Mount Haven Residents were previously assured they would not be overlooked. I expect the harbour houses will be altered. I have also asked that provision would be made for […]

  • Cllr. Derek Mitchell said he’s really pleased Greystones harbour boardwalk is currently being built. The developer is currently cutting the large steel piles to the same height and will then put a concrete deck on top during 2017. The walk on the inside of the marina will be closed when this is going on and […]

  • Work has started on the permanent Marina building to replace the temporary office for the Harbourmaster and toilets/showers. This will have a restaurant on the first floor which should be a good addition to the area. This should be complete by the end of the year. Meanwhile the Marina Village is expected to have 50 […]

  • The harbour developer explained the phasing of his moves to complete it. A lot of work is going on to complete the 5 clubs for handover this year. ‘I am delighted that the clubs are getting these facilities, which are costing €3.5m, it is a tremendous boost to the town’s sports facilities. No other town […]

  • The clubhouses for the Sea Scouts, Sailors, Divers, Anglers and Rowers are nearly complete and will be handed over to the clubs for final finishing in early December. I also notice that long hours, including weekend work, are being worked on the large public square. I anticipate that this will be open before next Summer. […]